ance  may  be  chaired  by  the  presiding organization  of  the comple-
            tion  acceptance  or  by  the  entrusted  legal  person  according  to  the
            size and  importance of  the  project.
            6.2 .2   The  diversion  (closure)  acceptance  shall  satisfy  the  fol-
            lowing  conditions:
                1   Diversion  works  has  been  completed  and  ready  for  pass-
            ing  through  water.  It  does  not  affect  other  construction  when  it
            is  in  use.
                2   Underwater  concealed  works  for  diversion  is  completed
            and  has  passed  acceptance.
                3   River  closure  plan  is  done  and  all  preparations  are  fin-
            ished.
                4  Construction  plan  for  flood  period  has  been  approved  by
            the  authorized  flood  control  headquarter  and  relevant  measures
            have  been  adopted.
                5   Relocation of resettlement  people and clear-up of the res-
            ervoir  bottom  under  raised  water  level  after  river  closure  have
            been  completed  and  passed  acceptance.
                6   Obstruction  and  barriers  on  navigable  rivers  are  re-
            moved.
            6 .2.3   The  diversion  (closure)  acceptance  shall  include  the  fol-
            lowings:
                1   Examine  whether  underwater  works,  concealed  works
            and  diversion  works  ( river  closure  works)  meet  the  require-
            ments  for  the  diversion  (closure).
                2   Examine  the  completion  situation of  land  requisition,  re-
            settlement  and  clearing  up  of  the  reservoir  bottom.
                3   Review  the  closure  plan,  the  measures  and  the  prepara-
            tions  for  the  diversion  (closure).
                4   Examine  the  implementation  of  measures  for  tackling