ance may be chaired by the presiding organization of the comple-
tion acceptance or by the entrusted legal person according to the
size and importance of the project.
6.2 .2 The diversion (closure) acceptance shall satisfy the fol-
lowing conditions:
1 Diversion works has been completed and ready for pass-
ing through water. It does not affect other construction when it
is in use.
2 Underwater concealed works for diversion is completed
and has passed acceptance.
3 River closure plan is done and all preparations are fin-
ished.
4 Construction plan for flood period has been approved by
the authorized flood control headquarter and relevant measures
have been adopted.
5 Relocation of resettlement people and clear-up of the res-
ervoir bottom under raised water level after river closure have
been completed and passed acceptance.
6 Obstruction and barriers on navigable rivers are re-
moved.
6 .2.3 The diversion (closure) acceptance shall include the fol-
lowings:
1 Examine whether underwater works, concealed works
and diversion works ( river closure works) meet the require-
ments for the diversion (closure).
2 Examine the completion situation of land requisition, re-
settlement and clearing up of the reservoir bottom.
3 Review the closure plan, the measures and the prepara-
tions for the diversion (closure).
4 Examine the implementation of measures for tackling