Page 21 - Water Standards
P. 21

5  Acceptance of Contracted
                             Project Completion



            5. 0.1  Acceptance of contract project completion shall be car­
            ried out after the construction works written in the contract have
            been completed.  W h e n  the contracted project refer to only one
            unit project  (or one sub-unit project), the unit project  (or sub­
            unit project) acceptance should be carried out together with the
            acceptance of the contracted project completion,  and shall meet
            relevant acceptance conditions.
            5.0.2  Acceptance of contracted projects shall be chaired by a
            legal person.  The acceptance working group shall consist of the
            legal person, representatives from designer, supervisor, contrac­
            tor, operation and management organizations as well as major e­
            quipment manufacturers  ( suppliers).  If  necessary,  other  ex­
            perts m a y  be invited.
            5.  0. 3  Member s  of the acceptance working group shall have rel­
            evant professional knowledge or occupational qualifications,  and
            at least half of the members shall possess the professional title of
            engineer or senior engineer.  Each institution should not nomi­
           nate more than 2 representatives.
           5.  0. 4  W h e n  the contracted project is completed and meets the
           acceptance conditions, the contractor shall submit an application
           to the  legal  person, with  the  contents  as  written  in  Article
           3. 0. 3. T he  legal person shall decide whether to carry out the ac­
           ceptance within 15  working days after the application report is
           received.
           5. 0. 5  The acceptance of contracted project completion shall meet