of main technologies as well as the construction conditions.
4 Examination of operation conditions for projects planned
to be commissioned.
5 Examination of remaining problems and treatment situa
tion of the previous acceptances.
6 Assessment of the quality of completed works.
7 Tackling suggestions for problems found in the accept
ance.
8 Discussion and passing of the appraisal report for stage
acceptance.
6.1. 5 Stage acceptance shall include the following procedures:
1 A n on-site investigation should be conducted on the con
struction situation and relevant data should be checked and read.
2 Meetings should be held for making:
1) Announce the list of stage acceptance committee m e m
bers.
2) Listen to the work reports by the organizations involved in
the project.
3) Discuss and pass the appraisal report for stage accept
ance.
4) As k representatives from the acceptance committee
and organizations to sign the appraisal report.
6.1. 6 Annex G shows the appraisal report format for stage ac
ceptances. The appraisal report shall be sent to relevant institu
tions by the presiding organizations, within 20 working days af
ter getting its approval.
6. 2 Diversion (Closure) Acceptance
6.2.1 Before diversion (closure), the diversion (closure) ac
ceptance shall be carried out. The diversion (closure) accept