the following conditions:
1 All projects and work within the scope of contract have
been completed.
2 Projects have been accepted and qualified according to
stipulations.
3 Initial values and all monitoring data during construction
period have been recorded by instruments and equipment.
4 Quality defects have been corrected according to the re-
quirements and accepted.
5 Settlement account of project completion has been closed.
6 Construction site has been cleared.
7 Files that shall be transferred to the legal person have
been sorted out.
8 Other conditions written in the contract are satisfied.
5. 0. 6 The acceptance of contracted project completion includes
the following contents:
1 Examination of the completion situation of the project
and works in the contract.
2 Examination of the clearing condition of the construction
site.
3 Examination of the operation situation for commissioned
projects.
4 Examination of the collection situation for acceptance da-
ta and documents.
5 Assessment of quality levels of the construction.
6 Examination of the completion settlement account of the
project.
7 Examination of the remaining problems and the treat-
ment situations for previous acceptances.
8 Treatment suggestions for problems found in the accept-