Page 17 - Water Standards
P. 17
requirements of contract specification.
2 Evaluate the construction quality levels.
3 Make suggestions for problems discovered during the ac-
ceptance.
3.0.6 The acceptance of sub-unit projects shall follow the pro-
cedures below:
1 Listen to the report about construction and quality evalu-
ation of item projects by the contractor.
2 Examine the completion situation of the project and con-
struction quality on site.
3 Examine the quality evaluation of item projects and rele-
vant files.
4 Discuss and pass the appraisal report (table) of accept-
ance of sub-unit projects.
3. 0. 7 The treatment situation for remaining problems in the
acceptance of sub-unit projects shall have written records and be
signed off by the representatives of relevant responsible institu-
tions. Written records shall be filed together with the appraisal
report of acceptance of sub-unit projects.
3. 0. 8 The format of appraisal report of acceptance of subdivi-
ded projects is shown in Annex C. The appraisal report of ac-
ceptance of subdivided projects shall be submitted to the relevant
institutions by the legal person within 20 working days after its
approval.