requirements  of contract  specification.
               2  Evaluate  the construction  quality  levels.
               3   Make  suggestions for problems discovered during the ac-
           ceptance.
           3.0.6  The acceptance of  sub-unit  projects  shall  follow  the  pro-
           cedures  below:
               1   Listen to the report about construction and quality evalu-
           ation of item  projects  by the  contractor.
               2  Examine  the completion  situation  of the  project and con-
           struction  quality on  site.
               3  Examine  the quality evaluation of item projects  and  rele-
           vant  files.
               4  Discuss  and  pass  the  appraisal  report  (table)  of  accept-
           ance of sub-unit  projects.
           3. 0. 7   The  treatment  situation  for  remaining  problems  in  the
           acceptance of sub-unit  projects  shall  have written  records  and  be
           signed  off  by  the  representatives  of  relevant  responsible  institu-
           tions.  Written records  shall  be  filed  together  with  the  appraisal
           report  of acceptance of sub-unit  projects.
           3. 0. 8  The  format  of  appraisal  report  of  acceptance  of  subdivi-
           ded  projects  is  shown  in  Annex  C.  The  appraisal  report  of  ac-
           ceptance of subdivided projects shall  be submitted  to the relevant
           institutions  by  the  legal  person  within  20  working  days  after  its
           approval.