representative to the meeting.
4. 0. 5 The acceptance of unit projects shall meet the following
conditions:
1 All sub-unit projects are completed and qualified.
2 The remaining problems found in the sub-unit project ac-
ceptances are solved and accepted, any remaining unsolved prob-
lems do not affect quality assessment of the unit projects and
there are treatment suggestions approved by the supervisor.
3 Other terms in the contract are satisfied.
4. 0. 6 The acceptance of unit projects shall include:
1 Check whether the project has been completed in line
with the approved design.
2 Assess quality of project construction.
3 Check the treatment situation for the remaining prob-
lems of the sub-unit project acceptance and relevant records.
4 Give treatment suggestions for problems of the accept-
ance.
4. 0. 7 The acceptance of unit projects shall follow the proce-
dures below:
1 Listen to the construction reports given by the organiza-
tions involved in the project.
2 Examine the completion situation and project quality on
site.
3 Examine relevant documents and files for the acceptance
of the sub-unit projects.
4 Discuss and pass the appraisal report for the acceptance
of unit projects.
4. 0. 8 Annex D is the format for unit projects acceptances. A f-
ter the appraisal report of the acceptance of unit projects has
been passed, it shall be sent within 20 working days to relevant