6 Stage Acceptance
6.1 General Requirements
6.1.1 The stage acceptance shall include diversion ( closure)
acceptance, impounding acceptance, acceptance of turbine-gener-
ator startup and others requested by the presiding organisation
according to the needs of the construction project.
6. 1. 2 The stage acceptance shall be chaired by the presiding
organization or its entrusted organization for completion accept-
ance. The stage acceptance committee consists of representatives
and relevant experts from the acceptance presiding organization,
quality and safety supervision organization and operation and
management organization. Officials from the local government
and relevant departments may be invited if it is necessary.
The organizations involved in the project shall appoint rep-
resentatives to attend the stage acceptance and sign on the ap-
praisal report as the organizations being accepted.
6. 1. 3 When the construction is ready for the stage acceptance,
the legal person shall submit an application ( see Annex F for
contents). The application shall be reviewed by the supervision
and management organization and then reported to presiding or-
ganization who should give a decision for an agreement or a disa-
greement within 15 working days after it is received.
6. 1. 4 Stage acceptance shall include the following contents:
1 Examination of the appearance and quality of completed
projects.
2 Examination of the construction situation.
3 Examination of uncompleted projects and implementation