navigation obstruction  problems.
               5  Assess  the quality  of completed  works  related  to  the  riv-
            er closure.
               6   Give  tackling  suggestions  for  problems  found  in  accept-
            ance.
               7   Discuss  and  pass  the  appraisal  report  for  stage  accept-
            ance.
            6.  2. 4   If the diversion works  (river closure)  is divided  into sev-
            eral  phases ,  the  diversion  ( closure)  acceptance  should  also  be
            carried out  in  stages.

                  6. 3  Acceptance of Reservoir  Impoundment

            6.3.1   The  acceptance  of  reservoir  impoundment  shall  be  car-
            ried  out  before  the  impoundment.  The  acceptance  of  reservoir
            impoundment  shall  be  chaired  by  the  presiding  organization  of
            completion  acceptance  or  the  entrusted  legal  person  according  to
            the scale and  importance of the  project.
            6.3.2  The  acceptance  of  reservoir  impoundment  shall  meet  the
            following  conditions:
                1   The  external  appearance  of  water  retaining  structures  meets
            the requirements of the impounding  water level.
               2   Resettlement  of  affected  residents  and  reservoir  bottom
            clearing  has  been  completed  and  pass  the  acceptance.
               3   The  discharge  structure  used  after  impoundment  is  al-
            most  completed  and  satisfies  requirements  of  overflowing.
               4  Instruments  and  equipment  for observation have  been in-
            stalled  and  tested  according  to  the  design,  and  the  initial  values
            and  observation  data  during  construction  period  have  been  ob-
           tained.
               5   Construction  plan  and  measures  for  uncompleted  works