Page 31 - Water Standards
P. 31
dover group while the operation management organization, con-
tractor and supervisor as the vice group leaders. The group shall
consist of staff from the operation management organization,
contractors for civil works and equipment installation, major e-
quipment manufacturers (suppliers) and supervisor. The group
is responsible for the inspection on completion situation and qual-
ity of civil works, metal structures and equipment installation as
well as handovers of technical documents, drawings, spare parts
and special tools etc.
6. 4. 5 The acceptance committee for turbine-generator startup
has the following major work items:
1 Listen to the reports of project legal person, designer,
supervisor, contractor and operation management organization as
well as the commissioning command group and acceptance han-
dover group; review related documents; examine whether the
status of the installation of turbine-generator, accessory equip-
ment, electrical equipment and construction of civil works and
quality meet the design requirements and standards stipulated by
the contracts, and whether they satisfy the requirements of tur-
bine-generator startup.
2 Check all preparations before turbine-generator startup
and the requirements in Article 6. 4. 2 and the others proposed by
the acceptance committee. Tackling suggestions for unqualified
items and remaining problems shall be proposed.
3 Review and approve the turbine-generator startup test
procedure, operation code and commissioning plan; determine
the date of the first time turbine-generator startup.
4 Prepare appraisal report of startup acceptance ,and de-
termine the list of handover items.
6. 4.6 For commissioning of turbine-generator startup, a tur-