tion, and the format for the completion acceptance working report and
its main contents are shown in Annex K and Annex L.
8. 1. 3 If the completion acceptance of the project fails to pro
ceed on schedule, the legal person shall submit a special applica
tion report to the presiding organization for delayed acceptance.
The application report shall include the main reasons of delay ac
ceptance and expected extension of time.
8. 1. 4 If there is still an amount of uncompleted work, which
does not affect normal operation and meets relevant financial pro
visions, and the legal person has made necessary arrangements
for the uncompleted work with the approval of the presiding or
ganization, the completion acceptance m a y he carried out.
8. 1. 5 The completion acceptance is divided into two stages in
cluding the technical pre-acceptance of completion and the c o m
pletion acceptance.
8. 1. 6 The completion acceptance shall follow the procedures
below :
1 The legal person organizes self-inspection for the c o m
pletion acceptance.
2 The legal person submits the application report of c o m
pletion acceptance.
3 The presiding organization approves the application re
port of completion acceptance.
4 The technical pre-acceptance of completion is carried out.
5 A completion acceptance meeting is held.
6 The appraisal report of completion acceptance is printed and
dispatched.
8. 2 Self-inspection for Completion Acceptance
8. 2. 1 Th e legal person shall organize self-inspection before ap