acceptance.
            8. 4. 4  The technical pre-acceptance of completion shall follow
            the procedures below:
                1   Examine the construction situation on site and review
            relevant construction documentation.
                2  Listen to working reports from the legal person, the de­
            signer, supervisor and contractor, the quality and safety supervi­
            sion organization and the operation management organization.
                3  Listen to the sampling inspection report for project quality.
                4  Professional working groups to discuss and give sugges­
            tions.
                5   Discuss and  pass the technical pre-acceptance working
            report for completion.
                6  Draft the appraisal report of completion acceptance.
            8. 4. 5  Working report of technical pre-acceptance for comple­
            tion shall be an attachment of the appraisal report of completion
            acceptance, and the format is shown in Anne x M.

                          8. 5  Completion Acceptance

            8. 5. 1  Th e completion acceptance committee shall consist of the
            representatives and experts of the presiding organization,  local
            people’s government, water administrative department,  quality
            and  safety  supervision  organization,  investors  and  operation
            management organization.  Th e committee m a y  have chair person
            and several deputies and members.  The chair person shall be one
            of the representatives from the presiding organization.
            8.5.2  The legal person,  designer, supervisor,  contractor and
            the equipment manufacturers  (suppliers) shall have representa­
            tives to participate in the completion acceptance,  answer ques­
            tions from the committee and sign on the appraisal report of ac­