9  Project Handover and Handling
                            of Leftover Problems


                      9. 1  Project Transfer and Handover

            9. 1. 1  W h e n  the completion acceptance of a contract project has
            been approved, the legal  person and contractor shall  nominate
            persons responsible for project transfer and handover within 20
            working days,  with complete written records and signatures of
            both parties.
            9. 1. 2  The legal person and the contractor shall finish transfer
            and handover of the project and file documents within specified
            time in the construction contract or the appraisal report of ac­
            ceptance.
            9. 1. 3  During the transfer and handover of specific project, the
            contractor shall submit warranty for project quality to the legal
            person and the format of warranty is shown in A nnex ().  The
            contents of warranty shall conform to the terms and reference of
            the contract.
            9. 1. 4  Th e validity of warranty shall commence from the c o m ­
            pletion acceptance,  except  for  those  contracts  which  stipulate
            otherwise.
            9. 1. 5   Project  legal  person shall  issue a certificate of project
            completion to the contractor within 20  working days after the
            warranty of project quality and other documents related to pro­
            ject completion have been provided and clear up of construction
            site has been finished.  The format of the certificate is shown in
            A nnex P.
            9. 1. 6  After handover, the legal person shall transfer the pro­