ceptance.
           8. 5. 3  The completion  acceptance meeting  shall  include the  fol-
           lowing  procedures:
               — Check  construction  situation  on  site  and  review  relevant
                  documents.
                —The meeting  shall  be  held  to:
                  1)  Announce the  name  list  of  the acceptance  committee.
                  2)  Listen to the working  report  of  the  construction  man-
                     agement.
                  3)  Listen  to  the  working  report  on  the  technical  pre-ac-
                     ceptance of  completion.
                  4)  Listen  to  other  reports  designated  by  the  acceptance
                     committee.
                  5)  Discuss and pass the appraisal  report of the completion
                     acceptance.
                  6)  Ask members  and  representatives  from  the  acceptance
                     committee and  acceptance  organization  to  sign  on  the
                     appraisal  report of the  completion acceptance.
           8. 5. 4   If project quality reaches the qualified level or above,  the
           quality  conclusion  of  the  completion  acceptance  shall  also  be
           qualified.
           8. 5. 5   The  appraisal  report  format  for  the  completion  accept-
           ance is  shown  in  Annex  N.  The  appraisal  report  of  the  comple-
           tion  acceptance  shall  be  submitted  to  the  relevant  organizations
           by the  presiding  organization  within  20  working  days  after  it  is
           approved.