8  Completion  Acceptance


                           8. 1  General  Requirements


            8.1.1   When  a  constructed  project  satisfies  the  conditions  of
            completion  acceptance,  the  legal  person  shall  submit  an  applica-
            tion  report  to  the  legal  person  acceptance  supervision  organiza-
            tion and  presiding organization  (see  Annex I  for more details).
            8.1. 2  The  completion  acceptance  shall  meet  the  following  con-
            ditions:

                1   The  project  has  been  completed  according  to  the  approved
            design.
                2   Major design  changes  have  been  approved  by the  organi-
            zation  with  authority.
                3   Each  of  the  unit  projects  can  be  operated  normally  and
            all  the  turbine-generators  are in  operation.
                4   Turbine-generator  commissioning  term  has  ended,  and
            hydraulic  structures  have  experienced  one  flood  season  and  one
            freezing  season.
                5   Problems  discovered  in  the  previous  acceptances  have
            been  solved.
                6   Acceptances of  all  special  items  have  been  approved.
                7   Working  report  on  quality  and  safety  supervision  has
            been  submitted,  and  project  quality  is  qualified.
                8   Financial  reports  of  final  accounts  of  state-financed  pro-
            jects  have  been  audited,  and  the  problems  found  by  the  audit
            have  been  fixed  and  the  report  of  the  fixed  problems  has  been
            submitted.
                9   Documents  for  completion  acceptance  are  ready  for  inspec-