Page 30 - Water Standards
P. 30
tested.
8 Operation management organization is set up and the staffs
are employed and meet the requirements for turbine-generator star-
tup.
9 Protective measures related to safety and fire control for
turbine-generator startup are put into practice.
10 Rules and regulations related to on-site safety operation
specifications are drawn up.
6. 4. 3 The acceptance of the first (last) turbine-generator star-
tup shall be chaired by the turbine-generator startup acceptance
committee established by the presiding organization of comple-
tion acceptance or by an organization entrusted. The acceptance
for the rest turbine-generators' startup shall be chaired by the
turbine-generator startup acceptance group organized by the legal
person. Representatives of local grid enterprises shall also join
the acceptance committee (group).
6 .4 .4 Under the turbine-generator startup committee, a com-
missioning commanding group and an acceptance handover group
shall be set up for undertaking specific work.
The project technical leader of the installation contractor
serves as the leader of the commissioning commanding group
while the technical leader of the operation and management or-
ganization as the vice group leader. The group shall be responsi-
ble for compilation of turbine-generator unit commissioning test
documents, and organizing commissioning and examination. Op-
erators on duty for turbine-generator unit commissioning shall
consist of staff from the unit installation contractor, operation
and management organization and major equipment manufactur-
ers (suppliers).
The legal person serves as the leader of the acceptance han-