3  Acceptance of Sub-unit  Projects




           3.  0. 1   The acceptance of  sub-unit  projects  shall  be  chaired  by a
           legal  person  (or  the  supervisor  entrusted  by  the  legal  person).
           The  acceptance  working  group  shall  consist  of  the  representa-
           tives  of  project  legal  person,  designer,  supervisor  and  contrac-
           tor,  and  equipment  manufacturers  (suppliers).
           3. 0. 2   The  members of the acceptance working group shall  have
           relevant  professional  knowledge or qualifications,  and each  insti-
           tution  should  not  nominate  more  than  2  representatives.
           3. 0. 3   When  a  sub-unit  project  satisfies  the  acceptance  condi-
           tions,  the  contractor  shall  submit  an application of  acceptance  to
           the  project  legal  person,  including  acceptance  scope,  inspection
           results  of  acceptance  conditions  and  proposed  time  for  accept-
           ance.  Project  legal  person  shall  reply  within  5  working  days  af-
           ter  receiving the  application  and give an answer to  the  contractor
           for agreement  or  disagreement.
           3. 0. 4   The  acceptance  of  sub-unit  projects  shall  meet  the  fol-
           lowing  conditions:
                1   All  item  projects  have  been  completed.
                2  Construction quality of the  completed  item  projects is  all
           qualified.  Relevant  quality  deficiencies  have  been  dealt  with  or
           have  obtained  the  treatment  suggestions  approved  by  the  super-
           visor.
               3  Other  conditions  written  in  the  contract  are  satisfied.
           3. 0. 5  The  acceptance  of  sub-unit  projects  shall  mainly  include
           the  followings:
                1   Check  whether  the  project  meets  the  design  standard  or
   11   12   13   14   15   16   17   18   19   20   21