Page 36 - 2010年全国水利发展统计公报
P. 36
2010年
全国水利发展统计公报
Completed of Fixed Assets Investment
unit:100 million Yuan
2,500
2,000
1,500
1,000
500
0 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
2000
Ⅱ. Key Water Projects
Harness of large rivers and lakes. There were 1,628 river harness projects under
construction that had spent 106.89 billion Yuan, accounting for 60.7% of the total
completed investment. The length of reinforced embankment was 4,530 km, of
which the newly added up to class-I and class-II standard embankment was 1,609
km long. There were 3,210 km of river channels were trained in 2010, and 2,237
km of which were completed. The accumulated investment in the Huaihe River
harness project completed 98%. Guidelines for Recent Activities of Furthering
Huaihe River Harness and Implementation Plan for Furthering Huaihe River
Harness were completed. Improvement of lowland in major plain was initiated in
the Huaihe River Basin. Training of main tributaries of major rivers such as four
rivers in Hunan, five rivers in Jiangxi, five rivers and one stream, Weihe River and
restoration of Dongting Lake and Poyang Lake are undertaken.
Reservoir projects. There were 382 water complexes under construction in
2010, with an accumulative investment of 101.40 billion Yuan, accounting for
52.8% of the total completed investment. Of those, 221 are reservoir projects with
an accumulated investment of 76.11 billion Yuan, accounting for 54.2% of the
total completed investment. The projects of Haibowan in Huanghe, Qingshan in