4 ) During construction, construction observation shall be
                                done well so as to know the stress of the rock and support⁃
                                ing structures and the failure zone range of the surrounding
                                rock, and the displacement and deformation in the rock
                                and the supports shall be observed.
                             5) When there are adjacent parallel caverns, the rock wall
                                shall be reinforced first, and then excavate downwards.
                             6) When constructing at a cavern intersection of the power⁃
                                house, the intersection shall be reinforced first. The rein⁃
                                forcement length shall be decided according to the sur⁃
                                rounding rock condition. The range of control shall be over
                                the extension of weak surfaces, not be less than 5m.
                       3   9   2  The flood provention for powerhouse construction shall meet
                       the following requirements:
                           1  Flood prevention measures shall meet the requirements in Ar⁃
                       ticle 2   2   4   Further more, specific measures with a reliable
                       economical method shall be selected through calculation, to ensure
                       security in the food season.
                           2  If the powerhouse structures are used for water retaining, the
                       underwater concrete shall be poured upto the safety elevation before
                       the flood season. All the holes or openings under flood level shall be
                       covered.
                           3  A tailwater bulkhead gate shall not be used to close the tail⁃
                       race during the flood season. If needed, the gate shall be reinforced
                       according to the water levels.
                       3   9   3  Powerhouse area drainage shall meet the following require⁃
                       ments:
                           1  Drainage system within the powerhouse area shall be con⁃
                       structed in line with the design drawings. A temporary drainage system
                       within powerhouse area during construction shall be arranged before
                                                                            1 7 9