Foreword (including acceptance basis, organizations and process)
1 C ontracted project overview
1. 1 Name and location of the contracted project
1. 2 M ajor construction contents of the contracted project
1.3 C onstruction process of the contracted project ( including com-
m encement and completion dates, m ajor m easures adopted in construction)
2 Scope of acceptance
3 Contract implement situation (including contract m anagem ent, project
completion situation and m ajor finished quantities, accounts settlem ent sit-
uation, e tc .)
4 Treatment of remaining problems discovered in the previous acceptances
5 Q uality evaluation of the contracted project
6 M ajor problem s and treatm ent suggestions
7 Com m ents and suggestions
8 Conclusions
9 Reservations (signature of the person w ith reservations)
10 Signature list of m em bers of w orking group for the contracted
project acceptance
11 A nnex: List of docum ents transferred by the contractors to the
legal person